US court rejects a request by tribes to block $10B SunZia energy transmission project in Arizona

Associated Press
by Susan Montoya Bryan
April 16, 2024

ALBUQUERQUE, N.M. (AP) — A federal judge on Tuesday rejected a request by Native American tribes and environmentalists to stop work on a $10 billion transmission line being built through a remote southeastern Arizona valley that will carry wind-generated electricity from New Mexico to customers as far away as California.

The project — approved in 2015 following a lengthy review — has been touted as the biggest U.S. electricity infrastructure undertaking since the Hoover Dam was built in the 1930s.

Two tribes joined with archaeologists and environmentalists in filing a lawsuit in January, accusing the U.S. Interior Department and Bureau of Land Management of refusing for nearly 15 years to recognize “overwhelming evidence of the cultural significance” of the remote San Pedro Valley to Native American tribes including the Tohono O’odham, Hopi, Zuni, and San Carlos Apache Tribe.

The suit was filed after Pattern Energy received approval to transmit electricity generated by its SunZia wind farm in central New Mexico through the San Pedro Valley, east of Tucson. The lawsuit called the valley “one of the most intact, prehistoric and historical … landscapes in southern Arizona,” and asked the court to issue restraining orders or permanent injunctions to halt construction.

Read the full article …