We should not have to choose between renewable energy and the land it works to protect.

29 September 2023

Appeal is filed

2023-10-02T21:35:35+00:00

Following the recent Arizona Superior Court decision to affirm the Arizona Corporation Commission’s November 2022 decision in favor of SunZia Transmission Project’s amendments — an Appeal has been filed on behalf of the Plaintiff Peter Else. The Arizona Superior Court judgement was formally issued on September 22, 2023, and the Appeal was filed less than four days later.

We remain committed, and continue to raise funds to support the legal effort. Please continue to share our fight with your communities. We and the San Pedro thank you so much for all of your support thus far!

Appeal is filed2023-10-02T21:35:35+00:00
4 September 2023

Superior Court decision

2023-09-07T16:59:43+00:00

On August 29, 2023, Maricopa Superior Court Judge Melissa Iyer Julian affirmed the Arizona Corporation Commission’s November 2022 decision to grant the SunZia Transmission Project amendments to their 2016 Certificate of Environmental Compatibility. The full ruling is presented here.

Statement by the plaintiff, Peter Else:

“I am understandably disappointed with the judge’s decision and respectfully disagree with it. I carefully reviewed the nine-page decision with my attorneys. While we understand the court’s desire to grant deference to the Corporation Commission, we strongly believe that deference has limits and that here, by failing to address the changed nature of the project, the Corporation Commission exceeded those limits. Deference should not result in passively allowing a private corporation to suddenly shift from repeatedly assuring multiple grid benefits to establishing a vertical monopoly that offers none of those benefits for Arizona. Accordingly, I intend to appeal.

Because of the unacceptable and avoidable impacts on the ecology of Arizona—Impacts which are not offset by any grid benefits to the citizens of this state—I will continue to oppose this effort to ship New Mexico wind energy to the high-priced electricity markets in California through the pristine San Pedro River Valley.

Also, I disagree with those who believe that poorly planned projects like SunZia should now be used as the pretext for granting the federal government even greater authority to sidestep legitimate state and local concerns over federal power line siting decisions. In addition to my legal effort with the Tully Bailey law firm at the state permit level, I will be communicating with interested media outlets about good and bad models for interstate transmission planning at the federal level.”

——————————–

Our fight is not over and we intend to continue to raise money for this prolonged legal endeavor. Please continue sharing with your contacts and donating. We remain grateful for and humbled by your support of the San Pedro River Valley.

Superior Court decision2023-09-07T16:59:43+00:00
18 August 2023

Update for the Superior Court hearing

2023-08-22T23:07:12+00:00

On Friday, August 22, 2023, the Arizona Superior Court judge heard testimony from the legal team representing the Arizona Corporation Commission and SunZia, and from the legal team representing Peter Else and Mr. Else. We anticipate a decision by the close of this week.

Update for the Superior Court hearing2023-08-22T23:07:12+00:00
15 August 2023

Archaeology Southwest’s Collaborative Opposition to the SunZia Power Line

2023-11-24T19:20:32+00:00

Archaeology Southwest website banner

August 15, 2023

On Head Shaking While Others Nod: Archaeology Southwest’s Collaborative Opposition to the SunZia Power Line
Archaeology Southwest
by John R. Welch, Bill Doelle, Skylar Begay, and Ashleigh Thompson for Archaeology Southwest

On August 4, 2023, Archaeology Southwest, the Tohono O’odham Nation, and the San Carlos Apache Tribe advised the US Bureau of Land Management (BLM), via a jointly submitted Notice of Dispute, of its failures to complete the historic property identification and Tribal Consultation processes required to move forward with the SunZia Southwest Transmission Project.

Read the full article

Archaeology Southwest’s Collaborative Opposition to the SunZia Power Line2023-11-24T19:20:32+00:00
29 June 2023

Final brief submitted to Arizona Superior Court

2023-08-16T01:40:15+00:00

June 29, 2023

The final written brief has been submitted in the Arizona civil case over SunZia Transmission Project’s permit.

On June 22nd, 2023, attorneys for citizen-plaintiff Peter Else filed in Arizona Superior Court their final written reply brief relating to the SunZia Transmission Project’s amended Certificate of Environmental Compatibility (CEC).

Plaintiff Else argues that SunZia’s original CEC, approved by the Arizona Corporation Commission (ACC) in 2016, was for a package deal that included benefits to Arizona that can no longer be assured. The amended CEC split the original project into two separate projects, which Else argues must now be reviewed independently. The ACC has statutory responsibilities to safeguard both Arizona’s electrical supply and Arizona’s most ecologically sensitive lands when it reviews a transmission proposal.

The brief asks that SunZia’s amended CEC be vacated and remanded to the ACC with instructions as to the applicable legal standards. The next step in the case is expected to be the scheduling of oral argument.

Plaintiff Else stated, “This case is significant. The federal government has fast-tracked the amendment process for this interstate transmission proposal, but Arizona statutes require the ACC to protect energy and environmental interests in this state.”

“My legal actions are being supported by other volunteers. These actions go beyond the simplistic notion that just because a major corporation is aligned with the politics of the current federal administration on a proposal that has a lot of megawatts and money involved, they must be on the right track for addressing climate change. Simplistic solutions often have unintended consequences. We want the ACC to consider those consequences for each of the two proposed lines.”

Final brief submitted to Arizona Superior Court2023-08-16T01:40:15+00:00
6 June 2023

BLM issues Record of Decision

2023-08-16T01:40:36+00:00

June 6, 2023

The Bureau of Land Management (BLM) issued a Record of Decision regarding SunZia. This may appear SunZia’s final approval, but not so. The BLM still needs to issue a Notice to Proceed, which is dependent on ALL agreements with state governments, local governments, and private parties being in place. Intervenor Peter Else’s legal challenge of the Arizona Corporation Commission’s November 2022 approval of SunZia is still in full motion.

BLM issues Record of Decision2023-08-16T01:40:36+00:00
12 May 2023

Opening brief filed

2023-08-16T01:41:39+00:00

May 12, 2023

Attorneys for citizen-plaintiff Peter Else filed in Arizona Superior Court an Opening Brief. This brief gives an excellent narrative of the history of the state process, as well as why the ACC was wrong in approving SunZia’s permits.

Opening brief filed2023-08-16T01:41:39+00:00
27 April 2023

Biden’s push for power lines

2023-08-16T17:59:11+00:00

April 27, 2023

Biden’s push for power lines
High Country News
by Jonathan Thompson

The process didn’t work as well in Arizona. There, sovereign Indigenous nations and conservation groups have attempted to get SunZia to reroute the line away from the fragile, biodiverse San Pedro River, because it would endanger birds and other wildlife and potentially damage culturally significant sites. But that didn’t seem to faze Arizona regulators, who tend to be more amenable to such projects and less responsive to environmental concerns than their New Mexican counterparts, and they unanimously approved the project. So far, the BLM has gone along with the proposed route, too.

This High Country News article provides a fairly balanced view of some of the environmental issues involved in providing renewable power to California via long-distance transmission, and touches on our opposition to SunZia.

Read the full article

Biden’s push for power lines2023-08-16T17:59:11+00:00
5 April 2023

Coalition protest to the Final Environmental Impact Statement

2023-08-16T18:17:43+00:00

April 5, 2023

Partnered with the Center for Biological Diversity, local conservation groups (Cascabel Conservation Association, Friends of Oracle State Park, and Lower San Pedro Watershed Alliance) have submitted a coalition protest to the Final Environmental Impact Statement for SunZia that was issued by the Bureau of Land Management in February 2023. A separate protest has also been submitted by Archaeology Southwest!

Coalition protest to the Final Environmental Impact Statement2023-08-16T18:17:43+00:00
29 March 2023

Riparian habitat threatened by proposed project

2023-08-16T01:43:04+00:00

March 29, 2023

Riparian habitat threatened by proposed project, San Pedro River advocates say
Arizona Republic
by Jake Frederico

The San Pedro River basin has been called a biological treasure in the desert. It’s a riparian refuge for more than 60 species of mammals, 14 species of fish and 41 species of reptiles and amphibians, and the millions of birds that use the river as a migratory flyway. But critics of a proposal to build a utility corridor along the west side of the river say it could threaten the health of the habitat and the survival of the wildlife.

Read the full article

Riparian habitat threatened by proposed project2023-08-16T01:43:04+00:00